Dude on the roof, installing the crescent window flashings
Drove by, and some guy was on the roof over the porch. He was installing the aluminum flashings that go around the crescent/vaulted window. They also shingled the roof over the porch.
Siding is getting there
They have installed the siding on the two sides and the back. They just have to do the front face and it will be done.
More siding, and dry-walling!
Whoa! I was surprised to see that the first floor was fully dry-walled. They finished the siding on the south side, but they haven’t started on any other area of the house yet.
Pillars have been installed
Drove by the house, and they installed the new pillars today. Looks good.
Home inspection + walk-thru today
The house looks fantastic inside. Framing is solid, floors are solid, the electrical is solid, …you get my drift. Everything looks like it is built well. They will be dry-walling in about 2 weeks, so I needed to get in there to take pictures of…
Fully bricked, garage floor poured
The house has been fully bricked. They have also poured the concrete for the garage floor – which is a surprise. Just a matter of time before they start the siding. I go inside the house tomorrow for an “Authorized Inspection”, which means I walk…
Better house pics
These are just some higher resolution pictures to go along with my last post. They were taken over the weekend, so not much was done.
Front porch is done, bricks finished on one side
They have finished the concrete front porch, and completed bricking one side of the house. That big pile of gravel has now been spread out into the garage and the front driveway. Things are moving along, ..but I’ve noticed the progress has slowed somewhat. Note:…